Programme updates: Warwick and Leamington
Below is a summary of the developer-led and funded s278 works as of Spring 2026.
Please note the program of works changes weekly. Please be reminded that as we move through autumn and winter months we may be constrained by various factors, such as inclement weather.
Developers and contractors are committed to delivering on all WCC program dates within given timescales.
Construction of a new Left In Left Out (LILO) junction for The Asps development
| Strawberry Fields, Gallows Hill - New Traffic Signals Junction | |
|---|---|
| Activity | A new ghost right turn junction for the development along with the installation of a toucan crossing point over Gallows Hill |
| Developer | William David |
| Contractor | Henderson Taylor |
| Status of works | In progress |
| Start date planned | February 2026 |
| Completion date | Summer 2026 |
| A452 Europa Way corridor new junction | |
|---|---|
| Activity | Construction of a new Left In Left Out (LILO) junction for The Asps development |
| Developer | Taylor Wimpey / Bloor Homes |
| Contractor | To be confirmed |
| Status of works | Technical review |
| Start date planned | April 2026 |
| Completion date | Winter 2026 |
| D7069 Glasshouse Lane East Roundabout and Cycleway | |
|---|---|
| Activity | Construction of new roundabout, footpaths and cyclepaths with associated street lighting and road markings |
| Developer | Vistry Homes |
| Contractor | To be confirmed |
| Status of works | In progress |
| Start date planned | To be confirmed |
| Completion date | Autumn 2026 |
Completed schemes
The ASPS – Leamington Spa/Banbury Road Widening - Scheme Complete Winter 2025
Scheme Overview - Creating drainage works, surfacing roads, upgrading the existing street lighting, installation of traffic signals and the introduction of new splitter islands. Further information can be found on the The ASPS update page.
Gallows Hill, Warwick - Scheme Complete April 2025
Scheme Overview - Additional work at the new Fusiliers Way junction to install new signage. Further information can be found on the Gallows Hill, Warwick 2025 update page.
D7069 Glasshouse Lane - Kenilworth School - Scheme Complete Winter 2025/26
The school was delivered on behalf of Kenilworth Multi Academy Trust (KMAT) working in partnership with Warwick District Council by Morgan Sindall Construction.
The new three-storey campus, for 2,200 students, opened in September 2023.


A4177 Birmingham Road, Hatton - Union View - Scheme Complete November 2024