Programme updates: Warwick and Leamington
Below is a summary of Section 278 (s278) programmes to date in Warwick and Leamington:
The ASPS - Leamington Spa / Banbury Road Widening
C5 Orton Road, Warton (Warton Allotments) | |
---|---|
Activity | Carriageway widening and road markings, new parking bays, new footpaths and construction of new access |
Developer | Countryside Partnerships |
Contractor | Lambes Construction |
Status of works | Under construction |
Start date planned | 5 May 2025 |
Completion date | August 2025 |
B4413 Longford Road (Wilsons Lane) Exhall | |
---|---|
Activity | Carriageway resurfacing and road markings, new footpaths and construction of new access |
Developer | Barwood Capital |
Contractor | Conlon Construction |
Status of works | Under construction |
Start date planned | April 2025 |
Completion date | TBC |
D7069 Glasshouse Lane East Roundabout and Cycleway | |
---|---|
Activity | Construction of new roundabout, footpaths and cyclepaths with associated street lighting and road markings |
Developer | Vistry Homes |
Contractor | TBC |
Status of works | TBC |
Start date planned | TBC |
Completion date | TBC |
Completed schemes
Gallows Hill, Warwick - Scheme Complete April 2025
Scheme Overview - Additional work at the new Fusiliers Way junction to install new signage. Further information can be found on the Gallows Hill, Warwick 2025 update page.
D7069 Glasshouse Lane - Kenilworth School - Scheme Complete October 2023
Warwick District Council approved plans to relocate Kenilworth School at Leyes Lane and the Sixth Form at Rouncil Lane to a new location at Southcrest Farm, Glasshouse Lane, as detailed on the Kenilworth School website.
The planning application for the demolition of Southcrest Farm and construction of a new school and Sixth Form College was approved by Warwick District Council on 19 December 2019.
Planning Application reference W/19/0655
The school is being delivered on behalf of Kenilworth Multi Academy Trust (KMAT) working in partnership with Warwick District Council by Morgan Sindall Construction.
The project will see Kenilworth School and Sixth Form relocated from its two existing sites to a new facility at Southcrest Farm, Glasshouse Lane in Kenilworth.
The new three-storey campus will offer places to 2,200 students.
The build programme is due to be complete in the summer of 2023, with the school opening to existing and new students in September 2023.
A4177 Birmingham Road, Hatton - Union View - Scheme Complete November 2024



Overview
Planning permission has been granted under Planning Application Reference: W/19/0933 for 150 New Homes/Dwellings (Class C3).
View the planning documents online
A new vehicular access from Birmingham Road has been approved as part of the planning application. The temporary vehicular access will be in place for sales and construction traffic from Birmingham Road in association with the works on the north side of Birmingham Road Hatton for Taylor Wimpey in accordance with the application submitted on 29 May 2019.
One or more of the conditions of this permission requires works to be carried out within the limits of the public highway. The developer must enter into a Highway Works Agreement made under the provisions of Section 278 of the Highways Act 1980 for the purposes of completing the works.