Programme updates: Warwick and Leamington

Below is a summary of the developer-led and funded s278 works taking place in Warwick and Leamington as of September 2025.

Please note the program of works changes weekly. Please be reminded that as we move through autumn and winter months we may be constrained by various factors, such as inclement weather.

Developers and contractors are committed to delivering on all WCC program dates within given timescales.

The ASPS – Leamington Spa/Banbury Road Widening
Activity The work will involve creating drainage works, surfacing roads, upgrading the existing street lighting, installation of traffic signals and the introduction of new splitter islands.

Update on The ASPS - Leamington Spa / Banbury Road Widening

Developer Taylor Wimpey and Bloor Homes
Contractor Fitzgeralds Contractors Ltd
Status of works Under construction
Start date May 2025
Completion date Winter 2025
D7069 Glasshouse Lane East Roundabout and Cycleway
D7069 Glasshouse Lane East Roundabout and Cycleway
Activity Construction of new roundabout, footpaths and cyclepaths with associated street lighting and road markings
Developer Vistry Homes
Contractor TBC
Status of works TBC
Start date planned TBC
Completion date TBC

Completed schemes

Gallows Hill, Warwick - Scheme Complete April 2025

Scheme Overview - Additional work at the new Fusiliers Way junction to install new signage. Further information can be found on the Gallows Hill, Warwick 2025 update page.

D7069 Glasshouse Lane - Kenilworth School - Scheme Complete October 2023

The school was delivered on behalf of Kenilworth Multi Academy Trust (KMAT) working in partnership with Warwick District Council by Morgan Sindall Construction.

The new three-storey campus, for 2,200 students, opened in September 2023.

the new Kenilworth School design

 

The plan for Kenilworth School

A4177 Birmingham Road, Hatton - Union View - Scheme Complete November 2024

Image of the completed road and pavement improvements showing a car and a crossing pointImage of the resurfaced road and improved markingsImage of improved road by housing estate

Overview

Planning permission has been granted under Planning Application  Reference: W/19/0933 for 150 New Homes/Dwellings (Class C3).

View the planning documents online

A new vehicular access from Birmingham Road has been approved as part of the planning application. The temporary vehicular access will be in place for sales and construction traffic from Birmingham Road in association with the works on the north side of Birmingham Road Hatton for Taylor Wimpey in accordance with the application submitted on 29 May 2019.

One or more of the conditions of this permission requires works to be carried out within the limits of the public highway. The developer must enter into a Highway Works Agreement made under the provisions of Section 278 of the Highways Act 1980 for the purposes of completing the works.