Programme updates: Warwick and Leamington

Below is a summary of the developer-led and funded s278 works winter 2025.

Please note the program of works changes weekly. Please be reminded that as we move through autumn and winter months we may be constrained by various factors, such as inclement weather.

Developers and contractors are committed to delivering on all WCC program dates within given timescales.

D7069 Glasshouse Lane East Roundabout and Cycleway
D7069 Glasshouse Lane East Roundabout and Cycleway
Activity Construction of new roundabout, footpaths and cyclepaths with associated street lighting and road markings
Developer Vistry Homes
Contractor McPhillips
Status of works In progress
Start date planned October 2025
Completion date December 2025

Completed schemes

The ASPS – Leamington Spa/Banbury Road Widening - Scheme Complete Winter 2025

Scheme Overview - Creating drainage works, surfacing roads, upgrading the existing street lighting, installation of traffic signals and the introduction of new splitter islands. Further information can be found on the The ASPS update page.

Gallows Hill, Warwick - Scheme Complete April 2025

Scheme Overview - Additional work at the new Fusiliers Way junction to install new signage. Further information can be found on the Gallows Hill, Warwick 2025 update page.

D7069 Glasshouse Lane - Kenilworth School - Scheme Complete October 2023

The school was delivered on behalf of Kenilworth Multi Academy Trust (KMAT) working in partnership with Warwick District Council by Morgan Sindall Construction.

The new three-storey campus, for 2,200 students, opened in September 2023.

the new Kenilworth School design

 

The plan for Kenilworth School

A4177 Birmingham Road, Hatton - Union View - Scheme Complete November 2024

Image of the completed road and pavement improvements showing a car and a crossing pointImage of the resurfaced road and improved markingsImage of improved road by housing estate