Programme updates: Nuneaton and Bedworth

Below is a summary of the developer-led and funded s278 works taking place in Nuneaton and Bedworth as of September 2025.

Please note the program of works changes weekly. Please be reminded that as we move through autumn and winter months we may be constrained by various factors, such as inclement weather.

Developers and contractors are committed to delivering on all WCC program dates within given timescales.

Higham Lane, Top Farm
Activity

Construction of a 4th arm on an existing signalised junction, to provide access into the Top Farm development and facilitate the opening of Higham Lane North Academy in Sept 2025

Developer Vistry in partnership with Warwickshire Property & Development Group
Contractor M Lambe Construction
Status of works In construction
Start date planned 10/02/2025
Completion date August/Sept 2025
C5 Orton Road, Warton (Warton Allotments)
C5 Orton Road, Warton (Warton Allotments)
Activity Carriageway widening and road markings, new parking bays, new footpaths and construction of new access
Developer Countryside Partnerships
Contractor Lambes Construction
Status of works Under construction
Start date planned 5 May 2025
Completion date August 2025

Completed schemes

B4413 Longford Road (Wilsons Lane) Exhall

Carriageway resurfacing and road markings, new footpaths and construction of new access.

Completed July 2025

A446 Lichfield Rd, Wishaw, The Belfry Hotel and Resort entrance

Safety improvements to prohibit the right turn movements for all vehicles exiting The Belfry onto A446 Lichfield Road.

Completed June 2025

 