Programme updates: Nuneaton and Bedworth
Below is a summary of the developer-led and funded s278 works taking place in Nuneaton and Bedworth as of September 2025.
Please note the program of works changes weekly. Please be reminded that as we move through autumn and winter months we may be constrained by various factors, such as inclement weather.
Developers and contractors are committed to delivering on all WCC program dates within given timescales.
Higham Lane, Top Farm | |
---|---|
Activity |
Construction of a 4th arm on an existing signalised junction, to provide access into the Top Farm development and facilitate the opening of Higham Lane North Academy in Sept 2025 |
Developer | Vistry in partnership with Warwickshire Property & Development Group |
Contractor | M Lambe Construction |
Status of works | In construction |
Start date planned | 10/02/2025 |
Completion date | August/Sept 2025 |
C5 Orton Road, Warton (Warton Allotments) | |
---|---|
Activity | Carriageway widening and road markings, new parking bays, new footpaths and construction of new access |
Developer | Countryside Partnerships |
Contractor | Lambes Construction |
Status of works | Under construction |
Start date planned | 5 May 2025 |
Completion date | August 2025 |
Completed schemes
B4413 Longford Road (Wilsons Lane) Exhall
Carriageway resurfacing and road markings, new footpaths and construction of new access.
Completed July 2025
A446 Lichfield Rd, Wishaw, The Belfry Hotel and Resort entrance
Safety improvements to prohibit the right turn movements for all vehicles exiting The Belfry onto A446 Lichfield Road.
Completed June 2025