Programme updates: Nuneaton and Bedworth
Below is a summary of all S278 works as of Winter 2026.
Please note the program of works changes weekly. Please be reminded that as we move through autumn and winter months we may be constrained by various factors, such as inclement weather.
Developers and contractors are committed to delivering on all WCC program dates within given timescales.
Scheme information
Details
Activity
Left-In Left-Out junction construction works on B4113 Pickards Way
Developer
Panatonni
Contractor
To be confirmed
Status of works
Due to start
Start date planned
Winter 2026
Completion date
Summer 2027
Completed schemes
B4413 Longford Road (Wilsons Lane) Exhall
Carriageway resurfacing and road markings, new footpaths and construction of new access.
Completed July 2025
A446 Lichfield Rd, Wishaw, The Belfry Hotel and Resort entrance
Safety improvements to prohibit the right turn movements for all vehicles exiting The Belfry onto A446 Lichfield Road.
Completed June 2025
C5 Orton Road, Warton (Warton Allotments)
Carriageway widening and road markings, new parking bays, new footpaths and construction of new access.
Completed August 2025
Higham Lane, Top Farm
Construction of a fourth arm on an existing signalised junction, to provide access into the Top Farm development and facilitate the opening of Higham Lane North Academy.
Completed November 2025