Programme updates: Stratford-upon-Avon

Below is a summary of the developer-led and funded s278 works as of Spring 2026.

Please note the program of works changes weekly. Please be reminded that as we move through autumn and winter months we may be constrained by various factors, such as inclement weather.

Developers and contractors are committed to delivering on all WCC program dates within given timescales.

Widening of the A423 Southam Bypass
Activity

Widening of the A423 Southam Bypass to create a ghost island right turn lane, which will provide access to the new Aldi store.

A423 Southam Bypass updates

Developer Aldi
Contractor Fitzgeralds Contractors Ltd
Status of works In progress
Start date planned August 2025
Completion date Spring 2026

 

The Shottery Relief Road
Activity

The relief road is designed to connect to the existing A46/A422 Alcester Road junction at Wildmoor Roundabout, which forms part of the National Highways network.

Developer Bloor
Contractor Montel
Status of works In progress
Start date planned Sept 2025
Completion date Summer 2026

 

B4632 Clifford Lane | Freshfields Nursery
Activity

Traffic calming measures on Clifford Lane at the junction with Freshfields Nursery, including new street lighting, new VAS, a speed limit reduction from 50mph to 40mph, new kerbing, changes to the road markings and localised carriageway widening, to create wider running lanes on the bend opposite Freshfields Nursery.

Developer Cala Homes
Contractor TBC
Status of works Planned
Start date planned TBC
Completion date TBC