Programme updates: Stratford-upon-Avon
Below is a summary of the developer-led and funded s278 works as of Spring 2026.
Please note the program of works changes weekly. Please be reminded that as we move through autumn and winter months we may be constrained by various factors, such as inclement weather.
Developers and contractors are committed to delivering on all WCC program dates within given timescales.
| Widening of the A423 Southam Bypass | |
|---|---|
| Activity |
Widening of the A423 Southam Bypass to create a ghost island right turn lane, which will provide access to the new Aldi store. |
| Developer | Aldi |
| Contractor | Fitzgeralds Contractors Ltd |
| Status of works | In progress |
| Start date planned | August 2025 |
| Completion date | Spring 2026 |
| The Shottery Relief Road | |
|---|---|
| Activity |
The relief road is designed to connect to the existing A46/A422 Alcester Road junction at Wildmoor Roundabout, which forms part of the National Highways network. |
| Developer | Bloor |
| Contractor | Montel |
| Status of works | In progress |
| Start date planned | Sept 2025 |
| Completion date | Summer 2026 |
| B4632 Clifford Lane | Freshfields Nursery | |
|---|---|
| Activity |
Traffic calming measures on Clifford Lane at the junction with Freshfields Nursery, including new street lighting, new VAS, a speed limit reduction from 50mph to 40mph, new kerbing, changes to the road markings and localised carriageway widening, to create wider running lanes on the bend opposite Freshfields Nursery. |
| Developer | Cala Homes |
| Contractor | TBC |
| Status of works | Planned |
| Start date planned | TBC |
| Completion date | TBC |