Programme updates: Stratford-upon-Avon
Below is a summary of all S278 works as of Winter 2026.
Please note the program of works changes weekly. Please be reminded that as we move through autumn and winter months we may be constrained by various factors, such as inclement weather.
Developers and contractors are committed to delivering on all WCC program dates within given timescales.
Widening of the A423 Southam Bypass to create a ghost island right turn lane, which will provide access to the new Aldi store.
Scheme information
Details
Activity
Developer
Aldi
Contractor
Fitzgeralds Contractors Ltd
Status of works
In progress
Start date
August 2025
Completion date
Spring 2027
The relief road is designed to connect to the existing A46/A422 Alcester Road junction at Wildmoor Roundabout, which forms part of the National Highways network.
Scheme information
Details
Activity
Developer
Bloor
Contractor
Montel
Status of works
In progress
Start date
Sept 2025
Completion date
Spring 2027
Traffic calming measures on Clifford Lane at the junction with Freshfields Nursery, including new street lighting, new VAS, a speed limit reduction from 50mph to 40mph, new kerbing, changes to the road markings and localised carriageway widening, to create wider running lanes on the bend opposite Freshfields Nursery.
Scheme information
Details
Activity
Developer
Cala Homes
Contractor
TBC
Status of works
Planned
Start date planned
TBC
Completion date
TBC