Programme of funded cycling schemes

The table below is a list of cycling schemes which have secured funding and are progressing towards construction. We expect to add more schemes to this list in the future. We are also preparing other schemes so that they can be added to the programme as soon as funding can be secured.

Programme of funded cycling schemes
Scheme/location Description Length Status Funding source Anticipated delivery timescale
A452 Kenilworth to Leamington Spa (K2L) An off-road route following the A452 north from Leamington Spa, crossing the River Avon and connecting to Kenilworth via the B4115 and Rocky Lane. 5km Design Warwickshire County Council TBC
A452 Kenilworth Rd to Leamington Spa Town Centre A segregated cycle track connecting the southern end of the K2L route near to Northumberland Road to Leamington Spa town centre 1.4km Design Getting Building Fund 2021/22
A429 Coventry Rd, Warwick A combination of segregated cycle track and shared use footway / cycleway between Primrose Hill and Coten End. 1.2km Design Getting Building Fund / Warwickshire County Council 2021/22
Vittle Drive / Ansell Way Extension of existing shared-use footway/cycleway to complete a missing link between Saltisford Common and St Marys Land. Toucan crossing at Saltisford. 0.2km Design Getting Building Fund 2021/22
Shakespeare Avenue (A429 Stratford Rd – A4089 Hampton Rd), Warwick Extension of existing shared-use footway on Stratford Rd and segregated cycle track on Shakespeare Avenue. 0.8km Design Getting Building Fund / Warwickshire County Council 2021/22
Myton Rd / St Nicholas Park cycle route enhancement (Phase 1) Widening of the existing shared-use path in St Nicholas Park between Myton Rd and Emscote Rd 0.5km Design Getting Building Fund 2021/22
Emscote Rd / Warwick New Road, Warwick / Leamington Spa Segregated cycle track between Coten End, Warwick and Regent Street, Leamington Spa 3km Feasibility Warwickshire County Council / Community Infrastructure Levy TBC
A47 / The Long Shoot (Nuneaton – Hinckley: eastern phase) Segregated cycle tracks / shared-use footway/cycleway between A5 and Eastboro Way 1.5km Design Warwickshire County Council / Active Travel Fund / Developer funding 2021/22
B4113 Bedworth – Bermuda Park Shared-use footway / cycleway Hill Street, Bedworth – Griff roundabout, Bermuda Park 0.9km Design Warwickshire County Council 2021/22
B4113 Bedworth - Coventry Shared-use footway / cycleway Trelawney Rd – Wilsons Rd. Toucan crossing Longford Rd. 1km Design Warwickshire County Council 2021/22
A47 Hinckley Rd, Nuneaton (Nuneaton – Hinckley: western phase) Segregated cycle track / shared-use footway/cycleway Eastboro Way – Leicester Rd 1.7km Design Warwickshire County Council / National Productivity Investment Fund 2021/22
Rugby Gateway – rail station / town centre (northern phase) Toucan crossing on A426 and traffic calming on Brownsover Lane 0.7km Design Active Travel Fund / Developer funding 2020/21 – 2021/22
A422 Alcester Rd, Stratford-upon-Avon Enhancements / extensions to existing cycle route 2.2km Design Getting Building Fund / Warwickshire County Council 2021/22
A3400 Birmingham Rd, Stratford-upon-Avon

Segregated cycle track Windsor Street – Maybird Shopping Centre

Enhancements / extension to existing shared use footway / cycleway north of Maybird

0.6km Design Warwickshire County Council / National Productivity Investment Fund Phased delivery between 2020/21 and 2022/23