A46 Stoneleigh Junction Improvement Scheme: Site Progress Update - May/June 2021
During April and May we have carried out bulk earthworks on Stoneleigh Road East which has included compaction trials on both sides of the A46.
-
A46 Stoneleigh Junction Improvement Scheme: Site Progress Update - April 2021
Work has been proceeding through March in establishing the permanent site compound and a second satellite compound near to the current Stoneleigh Road roundabout.
-
A46 Stoneleigh Junction Improvement Scheme: Site Progress Update - March 2021
Work has been proceeding in February in establishing the site and completing the main temporary accesses that will cater for future construction vehicle access.
-
March 2021 – Start of earthworks – Phase 1
Having built the site compound, March will see our contractor Colas-SIAC begin earthworks as part of Phase 1 (refer to the construction sequence page on this website for phasing details).
-
November 2020 – Main Works Award
The main works contract for the A46 Stoneleigh Junction Improvement Scheme has now been awarded to Colas-SIAC Limited.