Timescales

Highway works started in May 2018. The programme includes:

  • the timing of the developer led and funded schemes;
  • minimising travel disruption;
  • funding availability required to deliver the Council led schemes; and
  • design and construction challenges that may arise during programme delivery.

Construction schedule

The first three schemes are all developer led and funded – the indicative timescale for these schemes is:

Scheme ref Location Start date Duration Description
S278-4 Europa Way – Olympus Avenue to Shires Retail Park roundabout Mid March 2020 13 months 4 way signal controlled access junction with Olympus Avenue and Europa Way and dualling approximately 450m of Europa Way. The initial work will take place away from the highway and is not expected to cause disruption.
S278-2 Europa Way – south of Harbury Lane/Gallows Hill roundabout June 2018 10 months 4 way signal controlled access junction and dualling approximately 420m of Europa Way - now complete
S278-3 Gallows Hill – west of Europa Way/Harbury Lane roundabout Summer 2020 10 months 4 way signal controlled junction and widening of approximately 310m of Gallows Hill.