Reference No
and date received | Address | Proposal Summary | Decision Level / Status | Grid Reference |
NW8/06CC042
19/12/06 | Kingsbury Water Park Bodymoor Heath
Sutton Coldfield
Kingsbury
Warwickshire | Construction of an Education Outdoor Activity Centre. Works to include; construction of 373 m. sq centre with associated facilities, erection of fencing, creation of car parking area and creation of new access to site. Monitoring progress | Committee 03/04/2007
Granted
04/04/07 | SP202966 |
N299/06CC041
13/12/06 | Higham Lane School
A Business And Enterprise College
Shanklin Drive
Nuneaton
Warwickshire | Erection of 2.4m high and 1.8m high palisade fencing and access gate along the western boundary. Monitoring Progress | Delegated
Granted
01/02/07 | SP370929 |
N154/06CC040
08/12/06 | Abbey C E Infants School
Aston Road Nuneaton Warwickshire | Works to boundary of site including the demolition of boundary wall and the erection of 2 metre and 2.4 metre high palisade fencing with triple spiked tops, coloured green (ral6005).
Monitoring Progress | Committee
03/04/07
Granted
05/04/07 | SP356923 |
R1442/06CC039
07/12/06 | The route of the approved Rugby Western Relief Road from Cawston roundabout to, the Sow Brook. (See Drawing No H\A426-31\341) | Section 73 Application to amend Condition No. 26 of consent R/1442/02CC093 for the Rugby Western Relief Road. The amendment would allow the Rugby Western Relief Road to be constructed at a different level to that granted consent under R/1442/02CC093 between Cawston roundabout and the Sow Brook.
Monitoring Progress | Committee 13/03/2007
Granted
07/03/2007 | SP475747 |
NW313/06CC038
04/12/06 | Water Orton Primary School
Attleborough Lane
Water Orton
Warwickshire | Erection of 2.4m high palisade fencing and 4m wide double access gates to western boundary. All to be power coated green. Monitoring Progress | Committee
03/04/07
Granted
04/04/07 | SP175905 |
W225/06CC037
03/11/06 | Kingsway Community Primary School
Baker Avenue
Leamington Spa Warwickshire | Installation of a temporary unit to serve as a childrens centre plus provision for safe play area. Monitoring Progress | Delegated
Granted
08/12/2006 | SP286709 |
W399/06CC036
06/11/06 | North Leamington School And Manor Hall Educational Development Centre
Sandy Lane
Leamington Spa Warwickshire | Construction of a new 1500 pupil community school campus. Monitoring Progress | Committee
03/04/2007
Granted
09/05/07 | SP320680 |
N383/06CC035
25/10/06 | Warwickshire Fire & Rescue Service Training Centre
Leicester Road
Bedworth Warwickshire | Provision for the dismantling of chimney stacks. Monitoring Progress | Committee
23/01/2007
Granted 25/01/07 | SP357874 |
W11/06CC034
23/10/06 | Coten End Primary School Coten End
Warwick
Warwickshire | Erection of 2.4 metre high security fencing to create sports court. Monitoring Progress | Committee 23/01/2007
Granted
29/01/07 | SP289651 |
NW289/06CC033
12/09/06 | Woodside Primary School Maypole Lane
Baddesley Ensor Atherstone | Installation of modular unit for use by nursery school. Monitoring Progress | Delegated
Granted
24/11/2006 | SP276983 |
S433/06CC032
19/09/06 | Southam College
Welsh Road West
Southam Leamington Spa Warwickshire | Construction of a floodlit new generation artificial pitch plus associated changing facilities. Monitoring Progress | Committee 27/02/2007
Granted 28/02/2007 | SP413623 |
N109/06CC031
13/09/06 | Exhall Grange School & Science College Wheelwright Lane
Ash Green Bedworth Warwickshire | Construction of new hall block, gym block and covered link walkways. Extensions to existing 'north block', 'lancaster block', and 'man block'. Plus the provision for hard play areas. New access road, vehicular turning area, car parking areas and use of 'lancaster block' as i.d.s. offices. Monitoring Progress | Committee 21/11/2006
Granted
22/11/2006 | SP335842 |
NW70/06CC030
08/08/06 | Oakfield Junior School Southlands Atherstone Warwickshire | Erection of 2 metre high steel palisade security fencing and access gates, both vehicular and pedestrian, to a section of the eastern site boundary. All to have triple splayed tops and be colour green (ral 6005).
Monitoring Progress | Committee
17/10/06 Granted 18/10/06 | SP310973 |
R405/06CC029
01/08/06 | Bilton High School
Maths And Computing College
Lawford Lane Bilton
Rugby Warwickshire | Construction of extensions to form ICT suite and reprographics room. Monitoring Progress | Delegated
Granted
11/09/06
| SP479740 |
S993/06CC028
01/08/06 | Henley-In-Arden Primary School
Arden Road
Henley In Arden Warwickshire | Extension to existing building to create a hygiene facility and access ramp. Monitoring Progress | Delegated
Granted
04/09/06 | SP155659 |
N78/06CC027
01/08/06 | Stockingford Junior School Grove Road Stockingford Nuneaton Warwickshire | Construction of DDA access ramp.
Monitoring Progress | Delegated
Granted
06/09/06 | SP336912 |
W186/06CC026
01/08/06 | Coppice Road
Whitnash
Leamington Spa Warwickshire | Construction of a DDA access ramp.
Monitoring Progress | Delegated
Granted
04/09/06
| SP326630 |
S72/06CC025
27/07/06 | Henley In Arden High School
Stratford Road Henley-in-Arden Warwickshire | Construction of performance and dance teaching room with associated facilities. Plus the construction of 3 music practice rooms and disabled access ramp.
Monitoring Progress | Committee 07/09/2006
Awaiting
Decision | SP151654 |
W105/06CC024
26/07/06 | Lillington Nursery School Grange Road
Leamington Spa Warwickshire | Construction of a single storey building for early years child care facility.
Monitoring Progress | Delegated
Granted
15/09/06 | SP327671 |
S63/06CC023
13/07/06 | Thomas Jolyffe Primary School
Clopton Road Stratford-Upon-Avon Warwickshire | Creation of hard play area for infant school. Monitoring Progress | Delegated
Granted
08/09/06 | SP200560 |
N635/06CC022
06/07/06 | Wheelwright Lane Primary School
Wheelwright Lane
Ash Green Bedworth Warwickshire | Erection of double width access gates, pedestrian gate and barrier to front boundary. All to be 2 metre high steel palisade security fencing with triple splayed tops, coloured green. (ral 6005) Monitoring Progress | Delegated
Granted
25/08/06
| SP336842 |
W143/06CC021
18/05/06
| St. Johns House
Coten End
Warwick
Warwickshire | Erection of 2 metre high close boarded fencing to sections of boundary with matching metal frame gate, plus the replacement of 'deer' style timber rail double gates and post to forecourt side entrance. Monitoring Progress | Delegated
Granted
07/07/06 | SP287650 |
NW41/06CC020
19/04/06 | Blythe School
Packington Lane
Coleshill
Warwickshire | Erection of 1.8 metre high hollow section pale security fencing to the front (eastern) boundary of site. Incorporating vehicular and pedestrian access gates and to have black pale and gilt effect finial. Monitoring Progress | Delegated
Granted
28/11/06 | SP201876 |
W31/06CC019
12/04/06 | All Saints C Of E Junior School
Nelson Avenue
Warwick
Warwickshire | Erection of security fencing and access gates to sections of boundary.Monitoring Progress | Delegate6
Granted
13/06/06 | SP293660 |
N93/06CC018
30/03/06 | Former Leyland School Leyland Road Nuneaton Warwickshire | Erection of 2.4 metre high triple spiked palisade security fencing, incorporating vehicular access gates, to the northern and western site boundaries to be powder coated green. Monitor Progress. | Committee
13/06/06
Granted
14/06/06
| SP372903 |
R1442/06CC017
17/03/06 | Existing bend In the A4071 outside the Penthouse Cawston Rugby Warwickshire | A new 45m diameter roundabout at Potford's Dam Cawston Rugby to connect the existing A4071 to the proposed Rugby Western Relief Road.
Monitoring Progress | Committee
13/06/2006
Granted
13/06/06 | SP463722 |
S744/06CC016
15/3/06 | Ettington CE Primary School
Churchill Close Ettington Stratford-Upon-Avon Warwickshire | Construction of extension to main building to create a classroom, library and associated facilities.
Monitoring Progress | Committee
13/06/06
Granted
14/06/06
| SP270489 |
N189/06CC015
13/03/06 | Whitestone Infants School Magyar Crescent
Nuneaton
Warwickshire | Erection of 2.0 metre high steel palisade security fence with triple spiked splayed tops, to be colour green (RAL 6005) with incorporated pedestrian and vehicular access gates, all located to the front (north) boundary. Monitoring Progress | Committee
11/07/06
Granted 12/07/06 | SP381896 |
NW17/06CC014
06/03/06 | Polesworth High School
Dordon Road
Dordon
Tamworth
Warwickshire | Construction of a two storey international language centre. Monitoring Progress | Committee 02/05/2006
Granted
04/05/06 | SK258015 |
N203/06CC013
02/03/06 | Exhall Cedars Infant School
Trenance Road Exhall Warwickshire | Erection of 1.8 metre high palisade fencing, incorporating two pedestrian access gates and one double vehicular access gate to the eastern boundary. All to be coloured green.
Monitoring Progress | Delegated
Granted
20/04/06 | SP355858 |
N154/06CC012
16/02/06 | Hatter Space Community Education Centre
Upper Abbey Street Nuneaton Warwickshire | Provision for tarmacadam carpark extension.
Monitoring Progress | Delegated
Granted
13/04/06 | SP357921 |
W225/06CC011
16/02/06 | Kingsway Community Primary School
Baker Avenue Leamington Spa Warwickshire | Installation of two temporary units to create children's centre plus provision for small safe play area.
Monitoring Progress | Committee
07/09/06
Application Withdrawn | SP286709 |
NW70/06CC010
24/01/06 | Arden Hill
South Street Atherstone Warwickshire | Create level access to the building by constructing ramps. New ramps to front and side of building.
Monitoring Progress | Delegated
Granted
04/04/06 | SP311974 |
N234/06CC009
09/02/06 | Queens C E Junior School Bentley Road Nuneaton Warwickshire | Retrospective Planning Permission for the demolition of chimney stack.
Monitoring Progress | Delegated
Application
Withdrawn
| SP352917 |
W1495/06CC008
24/01/06 | Holly Walk House
56-58 Holly Walk Leamington Spa Warwickshire | Create level access to the building by constructing ramps. New ramps to front and side of building. Application Withdrawn | Delegated
Application
Withdrawn | SP322659 |
N267/06CC007
24/01/06 | Freeway Social Education Centre
Park Avenue Attleborough Nuneaton Warwickshire | Create level access to the building by constructing ramps. New ramps to front and side of building.
Monitoring Progress | Delegated
Granted
29/03/06
| SP371910 |
R440/06CC006
23/01/06 | 55 Clifton Road
Rugby Warwickshire | Create level access to the buildings by constructing ramps. New ramps to front and side of building.
Monitoring Progress | Delegated
Granted
08/05/06
| SP505751 |
W1460/06CC005
30/01/06 | Newburgh Primary School Kipling Avenue
Warwick
Warwickshire | Erection of 2.4 metre high steel weld mesh fencing to perimeter of site, incorporating two double vehicular, and two single pedestrian access gates to the same specification. Monitoring Progress | Committee
13/06/06
Granted
13/06/06
| SP272638 |
R309/06CC004
20/01/06 | Newton Hall
Lower Hillmorton Road
Rugby Warwickshire | Change of use of rooms from offices to youth offending team activities.
Monitoring Progress | Delegated
Granted
17/03/06 | SP516748 |
R573/06CC003
20/01/06 | Hillmorton Primary School Watts Lane
Hillmorton
Rugby
Warwickshire | Erection of 2.4 metre high steel palisade fencing with triple spiked tops, coloured green, to all boundaries apart from a section of western boundary. Plus incorporation of pedestrian and vehicular access gates to the same specification. Monitoring Progress | Committee
07/09/06
Withdrawn | SP537737 |
N299/06CC002
13/01/06 | Higham Lane School (Detached Playing Field) Ambleside Way
Nuneaton
Warwickshire | Erection of a 2.4 metre high steel palisade fence with triple spiked tops to the northern and eastern boundaries with the incorporation of double vehicular access gates to the same specification. Plus replacement of pedestrian gate to the front entrance and fencing along walkway to field to same specification but powder coated green. Monitoring Progress | Committee 16/03/2006
Granted
17/03/06 | SP374930 |
W186/06CC001
05/01/06 | St Margarets C Of E
Junior School
Coppice Road Whitnash
Leamington Spa
Warwickshire | Provision of a 100 squared metre tarmac
hardstanding parents waiting area with a
new pedestrian access off Coppice Road.
Monitoring Progress | Delegated
Granted
13/02/06 | SP326630 |